Evaluasi Proteksi Petir Eksternal dan Internal Pada Pembangkit Listrik Tenaga Surya 1 MW Cirata
External & Internal Lightning Protection Evaluation on Cirata 1 MW Solar PV Power Plant
Skripsi, 025 / 2023 / TPTLUndergraduate Theses from JBPTPPOLBAN / 2024-03-20 12:09:33
Oleh : 191724027 - Muhammad Thoriq Rizquloh (trizqulah@gmail.com)
Dibuat : 2024-03-20, dengan 4 file
Keyword : Petir, PLTS, Proteksi Petir Eksternal, Proteksi Petir Internal
Subjek : Lightning, Solar PV Power Plant, External Lightning Protection, Internal Lightning Protection
Pembangkit Listrik Tenaga Surya (PLTS) membutuhkan lahan yang terbuka dan luas supaya dapat beroperasi secara optimal. Hal ini menimbulkan ancaman akibat sambaran petir dimana secara statistik efek dari sambaran petir merupakan penyebab kerusakan PLTS terbesar kedua dengan presentase sebesar 26%. PLTS 1 MW Cirata merupakan PLTS milik PT. PLN Nusantara Power yang telah beroperasi selama kurang lebih 7 tahun sejak 2015. Dalam kurung waktu tersebut sistem proteksi petir eksternal maupun internal yang terpasang tidak diketahui telah memberikan perlindungan secara baik atau tidak. Maka dilakukan evaluasi terhadap sistem proteksi petir eksternal dan internal berdasarkan data-data eksisting dengan mengacu standar-standar terkait proteksi petir seperti IEC 62305, NFC 17-102 tahun 2011, SNI 03-7015, dan PUIPP. Berdasarkan evaluasi yang dilakukan, terminasi udara dari sistem proteksi petir eksternal hanya memberikan perlindungan sejauh 95,850 m yang membuat beberapa bagian modul PV tidak terlindungi. Kemudian terdapat jalur masuk listrik dari grid PLN sebesar 380 V AC yang tidak dilengkapi dengan arrester/ surge protection device sebagai proteksi petir internal. Rekomendasi yang diberikan pada sisi eksternal yaitu melakukan penggantian terminasi udara yang dapat memberikan radius proteksi sebesar 112,081 m dan penggeseran tower terminasi udara sejauh 4 m kearah timur. Kemudian pada sisi internal disarankan melakukan pemasangan SPD 380 V AC Tipe I+II, dengan maximum impulse current discharge 50kA untuk memberikan proteksi yang optimal. Kata Kunci: Petir, PLTS, Proteksi Petir Eksternal, Proteksi Petir Internal.
Deskripsi Alternatif :Solar PV Power Plants require open and spacious land in order to operate optimally. This poses a threat due to lightning strikes where statistically the effects of lightning strikes are the second largest cause of damage to PV Plants with a percentage of 26%. Cirata 1 MW Solar PV Power Plant is owned by PT PLN Nusantara Power which has been operating for approximately 7 years since 2015. During this time, the external and internal lightning protection systems installed are not known to have provided good protection or not. So, an evaluation of the external and internal lightning protection system is carried out based on existing data by referring to standards related to lightning protection such as IEC 62305, NFC 17-102 in 2011, SNI 03-7015, and PUIPP. Based on the evaluation conducted, the air termination of the external lightning protection system only provides protection as far as 95.850 m which leaves some parts of the PV module unprotected. Then there is an electricity inlet from the PLN grid of 380 V AC which is not equipped with an arrester / surge protection device as internal lightning protection. The recommendations given on the external side are to replace the air termination which can provide a protection radius of 112.081 m and shift the air termination tower as far as 4 m to the east. Then on the internal side it is recommended to install SPD 380 V AC Type I + II, with a maximum impulse current discharge of 50kA to provide optimal protection. Keywords: Lightning, Solar PV Power Plant, External Lightning Protection, Internal Lightning Protection.
Beri Komentar ?#(0) | Bookmark
Properti | Nilai Properti |
---|---|
ID Publisher | JBPTPPOLBAN |
Organisasi | |
Nama Kontak | Erlin Arvelina |
Alamat | Jl. Trsn. Gegerkalong Hilir Ds. Ciwaruga |
Kota | Bandung |
Daerah | Jawa Barat |
Negara | Indonesia |
Telepon | 022 201 3789 ext. 168, 169, 239 |
Fax | 022 201 3889 |
E-mail Administrator | erlin.arvelina@polban.ac.id |
E-mail CKO | erlin.arvelina@polban.ac.id |
Print ...
Kontributor...
- Pembimbing 1: Prof. Dr. Ir. Hermagasantos Zein, M.Sc.
Pembimbing 2: Siti Saodah, S.T., M.T., Editor: Erlin Arvelina
Download...
File : KELENGKAPAN SKRIPSI - 191724027.pdf
(1865168 bytes)
File : BAB 1 - 191724027.pdf
(493422 bytes)
File : BAB 2 - 191724027.pdf
(1192609 bytes)
File : BAB 5 - 191724027.pdf
(472706 bytes)